§ 7-47. Same—Rough-in and final; notice; time allowed.  


Latest version.
  • There shall be a rough-in inspection where desirable, and final inspection on each installation. For the rough-in inspection, the permit holder whose installation is ready for inspection shall allow the electrical inspector's office twenty-four (24) hours, Saturdays, Sundays and holidays recognized by the city excepted, before proceeding with the work or installations. The same notice shall be allowed for a final inspection.

(Ord. No. 7708, § 41, 3-3-77)